Utility Expansion Program & Resiliency

The Village of Estero’s Utilities Expansion Program (UEP) is a multi-phase public infrastructure initiative designed to eliminate septic tanks and package wastewater treatment plants, replacing them with central sewer and potable water systems to protect local waterways like the Estero River.

Key Project Goals

The Septic-to-Sewer conversion involves transitioning residential and commercial properties currently relying on private septic tanks and wells to central utility networks including removing smaller, outdated package wastewater treatment plants within the Village of Estero. The conversion will reduce environmental contamination and nutrient runoff flowing into the Estero River and local bays.

The initial targets focused on early conversion areas including Estero Bay Village, Sunny Groves, Cypress Bend, Estero on the River, County Road and Highlands Avenue. The work involves extending potable water lines, sanitary sewer lines, installing force mains along major corridors like US 41 and handling local neighborhood expansions (such as Broadway Avenue East and West).

Although the plans were started back in 2018, the Village has been hard at work attempting to optimize the Funding and Financials by agreeing on the range of available grants. This has proven to be both frustrating and extremely time-consuming, but necessary to try to limit the charges those involved in the conversion would have to pay. 

Several grants and debt financing procedures have been established through a combination of state appropriations (such as Florida Department of Environmental Protection grants), federal hazard mitigation funds and local debt financing/bonds.

The specific details are as follows:

The Village has secured a steady stream of annual state appropriations and FDEP legislative grants specifically designated for the septic-to-sewer transitions:

  • $2.5 Million (FY 2024–2025): Allocated directly toward initial project phases.
  • $1.6 Million (October 2025 Approval): The Village Council approved two separate FDEP grants of $800,000 each. One is dedicated to the Estero Orange Park Utility Extension Project (potable water mains, gravity sewers, and a lift station along See Street) and the other is for Broadway Avenue East Phase 1 (improvements along Sandy Lane).
  • $7.5 Million (FY 2023–2024): The largest single state funding injection secured for the broader expansion layouts.
  • $1.73 Million (FY 2022–2023): Early-stage grant funding utilized to kickstart design, surveying and engineering configurations.

Community Development Block Grants (CDBG-DR): The Village received a CDBG-Disaster Recovery grant with a $450,000 allocation to be administered via HUD and Lee County.

Major Federal Grants Currently In-Process: While the Village has applied for a massive $32.2 million to cover the majority of the seven Broadway West communities, management is aggressively tracking two primary pending items in advanced stages:

  • $16.5 million via FEMA’s Hazard Mitigation Grant Program (HMGP), targeted heavily at high-flood-risk communities along the river like Estero River Heights and Cranbrook Harbor.
  • $800,000 via the federal Non-Point Source Grant program to offset stormwater-adjacent utility runoff.

Estero Village Management aims to distribute project costs fairly while pursuing substantial external grant revenue.

Village Website on this Project

Last Updated:November 3, 2026