US-41 near County Road
The Sunny Grove project includes the construction of a new sanitary sewer force main out to a new force main being constructed along the east side of US-41 as part of the Estero River Park project. That new force main will connect to the existing Lee County Utilities force main on the north side of Corkscrew Road.
The Sunny Grove Park project includes construction of a new pump station facility with an on-site emergency generator adjacent to the existing Sunny Grove wastewater treatment plant (WWTP), removal of the existing WWTP facility, leaving the maintenance building and demucking/backfilling the percolation ponds.
Council approved Contract Addendum 02 for $2,540,946 with Wright Construction, Inc., for the Sunny Grove Park project.