Resilience for Estero

As part of the Village's Oct. 28, 2024, Corrective Action Plan required by FEMA, the Village agreed to review its Land Development Code floodplain regulations to make changes where appropriate. The Village's floodplain regulations had not been updated since Nov. 16, 2022. Due to the recent hurricanes, it became evident that some revisions were needed.

Staff has prepared changes to the ordinance, including the following:

  • Clarifiy the Variance Process due to inconsistent language in the Code
  • Non-conversion agreement for elevated homes
  • Clarify the specific use of FEMA Elevation Certificates for all flood hazard areas
  • Clarify the specific use of the FEMA Dry Floodproofing Certification form
  • Limit on partitioning enclosed areas below the flood

The Village Planning, Zoning and Design Board recommended that Council approve this ordinance.

As part of the resilience development plans for Estero, the Village purchased the land south of the Estero Post Office for $15 million to improve stormwater management and to designate the land "not for commercial use." The School District of Lee County had considered this parcel for a potential future school in Estero. The purchase will help prevent further commercial and residential development on the site.

A procedural item was adopted at the Jan. 21, 2025, Village Council meeting to empower the Village to use this asset to issue bonds and return cash to the Village for other priorities.

Although there has been some discussion about dredging the Estero River, the latest report indicates, as of August 2026, the Village of Estero management has not undertaken active physical dredging of the Estero River and its tributaries. Instead, municipal leaders have focused their river-restoration strategies and millions of dollars in funding on upstream flood mitigation, land preservation and water-pollution prevention.

As mentioned earlier, several significant land acquisitions and infrastructure initiatives are helping guide responsible, sustainable growth. These efforts reflect a strong commitment to environmental stewardship, recreation, and long-term community resilience.

Recent and ongoing projects include:

  • The preservation of 62 acres of recreational land northwest of US-41 and Corkscrew Road along the Estero River corridor.
  • The protection of 10 acres near River Oaks to maintain natural open space and conserve environmentally sensitive areas.
  • The dedication of 79 acres behind the post office on Three Oaks Parkway for enhanced flood management, including the installation of retention ponds to improve stormwater control.
  • The allocation of 20 acres near Via Coconut Point and Williams Road for the development of a community sports and recreation complex.

The Septic-to-Sewer transition also is an essential resilience and environmental improvement. This conversion is vital to reducing nutrient contamination in the Estero River and protecting the health of Estero Bay. While implementation has taken longer than originally anticipated, the delay reflects a deliberate effort to secure federal, state and county grant funding to help minimize homeowner costs. Hopefully, this issue will be resolved in the near future.

Last Updated:November 3, 2026