Estero Transportation & Capital Projects: What to Expect Over the Next 18 Months
Key Take-Aways
-
- Completed Milestones: Highlands Ave extension into Estero RiverPark is complete; Summercrest Community access from Corkscrew Road is re-routed via Sandy Lane and Design Parc Lane.
- Active Construction: Woodfield Project roundabout (US 41/Coconut Rd W) expected by Feb 2027; Aldi's right-in/right-out on East Corkscrew due by end of 2026; Corkscrew Rd East upgrades delayed to Feb 2027 due to material/utility access delays.
- Major Upcoming Projects: Broadway Ave W reconstruction (18-month timeline starting late 2026); Williams Ave W roundabout planned for early 2027 (6-month build).
- State Funding & Long-Term Planning: Funding requested for Corkscrew Rd 6-lane widening (I-75 to Three Oaks Pkwy) and intersection upgrades at Corkscrew/Three Oaks; BERT rail removal pending Jan 2027 agreements.
Published October 30, 2026 by Engage Estero
Written by

Mark Novitski
Consultant to Engage Estero
Transportation infrastructure throughout Estero is moving rapidly as local municipal leaders, Lee County, and the Florida Department of Transportation (FDOT) work to improve mobility, pedestrian safety, and roadway capacity. From key updates along Corkscrew Road and US 41 to long-term plans for the Bonita Estero Rail Trail (BERT), here is a comprehensive breakdown of recently completed projects, active construction, and upcoming infrastructure plans affecting Estero over the next 18 months.
Recently Completed Estero Infrastructure Projects
Local motorists and park visitors will notice recent traffic flow and access improvements across the Village of Estero:
- Estero RiverPark Access: Highlands Avenue has officially been extended into the Estero River Park, facilitating smoother park access.
- Summercrest Community Access Reconfiguration: The former entrance to the Summercrest Community from Corkscrew Road has been permanently closed with new curbing and sidewalks installed. A dedicated right-turn lane was added on Sandy Lane. Summercrest residents now access their neighborhood via either Sandy Lane or Design Parc Lane.
Map is interactive. Click on the blue pointers to learn more about the projects.
Currently Under Construction in Estero
Several major roadway projects and commercial access improvements are actively underway:
Woodfield Project Roundabout (US 41 & Coconut Road West)
Developers are constructing a new traffic roundabout at the southern entrance of the Woodfield development and Walden Center Drive.
- Expected Completion: February 2027.
Estero SportsPark Entrances
Work is actively progressing on primary access entrances to the Estero SportsPark via Coconut Point and Williams Road, with completion targeted in the near term.
Corkscrew Road East Improvements
Comprehensive upgrades along Corkscrew Road East—including new streetlights, landscaping, and multi-use paths—have experienced timeline adjustments. Originally scheduled earlier, completion is now set for February 2027 due to delays in weather, plant availability, and reclaimed water connection access.
Aldi Commercial Access on East Corkscrew Road
Construction of a right-in/right-out access point on East Corkscrew Road for Aldi is progressing. Under the development order, this infrastructure must be fully completed before the store can open to the public, with completion anticipated by calendar year-end.
Infrastructure Projects in Planning & Contract Award
Significant road widening, sidewalk enhancements, and intersection safety updates are slated to begin late 2026 through early 2027:
Broadway Avenue West Reconstruction
A 2-mile stretch of Broadway Avenue West is scheduled for full reconstruction to improve stormwater drainage, widen travel lanes, and upgrade pedestrian sidewalks.
- Contract Award: Expected Q4 2026.
- Construction Duration: Approximately 18 months.
Williams Avenue West Roundabout
Plans for a roundabout on Williams Avenue West (located in front of the Life Care Center of Estero) are advancing. Necessary land acquisition from the neighboring Fountain Lakes community is in final negotiations.
- Contract Award: Expected Q1 2027.
- Construction Duration: Approximately 6 months.
US 41 and Pelican Colony Boulevard Traffic Signal
FDOT approval for a new traffic signal at US 41 and Pelican Colony Blvd is nearing completion (expected early 2027). Local site communities have already committed funding, allowing construction to begin as soon as final FDOT authorization is granted.
Funding Requests & Inter-Agency Traffic Discussions
Corkscrew Road Corridor Widening & Intersection Upgrades
- I-75 to Three Oaks Parkway: The Lee County Board of County Commissioners (BOCC) is requesting a $6 million state appropriation to advance engineering and design plans for widening Corkscrew Road to 6 lanes between I-75 and Three Oaks Parkway. (Note: No updates are currently available for Corkscrew Road West from Three Oaks Parkway to US 41.)
- Three Oaks Parkway Intersection: The Village of Estero is requesting $1.2 million in state funding for dedicated turn lane improvements at the intersection of Corkscrew Road and Three Oaks Parkway.
Bonita Estero Rail Trail (BERT) Update
Following expected agreement executions and financial transfers in January 2027, Seminole Gulf Railroad will have up to two years to remove railroad tracks from local roadways across Bonita Springs and Estero. Municipal leaders remain hopeful that rail and tie removal will occur sooner.
Once cleared, the Lee County Department of Transportation, the Village of Estero, and Bonita Springs will grade and pave cross-road sections. As part of this realignment:
- The sidewalk/multi-use path along Estero Parkway will align seamlessly with the existing multi-use trail network.
- Road Crossing Impact: Rail removals will affect 1 Lee County road (Corkscrew Road) and 5 Village of Estero roads (Estero Parkway, Broadway Avenue East, Via Coconut Point, Williams Road, and Coconut Road).
Safety Discussions: US 41 & Sweetwater Ranch Road / Fountain Lakes Boulevard
Ongoing discussions continue between community leaders, Village staff, and FDOT regarding a potential traffic signal at US 41 and Sweetwater Ranch Road / Fountain Lakes Blvd. Local residents highlight safety concerns at this intersection, noting that traffic volume will increase with commercial developments, restaurants, and shops adjacent to Rapallo.
FAQs
Q: When will the Corkscrew Road East multi-use path and lighting project be completed?
A: The updates on Corkscrew Road East—including streetlighting, landscaping, and multi-use paths—are expected to be completed by February 2027 following delays related to weather and utility access.
Q: What improvements are planned for Broadway Avenue West in Estero?
A: A 2-mile section of Broadway Avenue West will undergo full reconstruction to improve drainage, widen lanes, and upgrade sidewalks. Construction is set to begin following contract award in Q4 2026 and will take approximately 18 months.
Q: What is the status of the Bonita Estero Rail Trail (BERT) track removal?
A: Final agreements are anticipated in January 2027. Following approval, Seminole Gulf Railroad will have up to two years to clear tracks and hardware, allowing Lee County and the Village of Estero to grade and pave cross-road sections across 6 affected local roads.
Q: Is Corkscrew Road being widened to 6 lanes in Estero, FL?
A: Lee County is currently seeking $6 million in state funding to advance design work for widening Corkscrew Road to 6 lanes from I-75 to Three Oaks Parkway.
Image Credit: Filip Cvjeticanin
Related Articles
Dangerous U-Turns by Large Commercial Trucks on Corkscrew Road in Estero
October 17, 2026
Village of Estero Supports Resident Concerns Over I-75 Expansion Impacts
September 15, 2026
I-75 Expansion Must Not Come at the Expense of Estero’s Quality of Life
September 11, 2026

At Engage Estero, we believe in the power of community. As a nonpartisan, nonpolitical, nonprofit, we conduct evidence-based research to provide unbiased information about local issues, helping you improve your quality of life.